Pocopson supervisors reveal revised roundabout plans

Project could start in 2013 to make intersection of Lenape-Unionville, Wawaset and Rt. 52 safer

By Kelli Siehl, Staff Writer, UnionvilleTimes.com

Pocopson township officials revealed revised plans to build a roundabout at Rt. 52, Wawaset and Lenape-Unionville roads. As seen here, Rt. 52 comes in from the bottom of the diagram, enters the roundabout and then bears left, with Unionville-Lenape Road at the top and Wawaset Road to the right. The driveway to the Pocopson Home would be moved north on Rt. 52 and seen to the lower right of the image.

POCOPSON — Finding your way around the township these days has been like circumventing a maze. Just when you’ve got it figured out, one route closes and another opens, reconfiguring the puzzle. Think of it as a brain teaser, an exercise designed to boost brain power, because it’s going continue for several more years at sites in and around the township.

At Monday’s Township Supervisors’ meeting, Consultant Project Manager for the state Department of Transportation (PennDOT), Paul Linahan, gave residents an update on the roundabout planned for the triangle which joins route 52 with Wawaset and Lenape-Unionville roads.

Supervisors’ Chair, Steve Conary gave those in attendance a brief history of the project which has been in the works for almost five years.  Conary said, “those obtuse angle intersections make it difficult to see traffic; difficult to merge.” Supervisors said traffic along 52 has steadily increased since the expansion of the Chester County Prison and the addition of the County Juvenile Detention Center.

Conary explained that experts looked at the site and determined that traffic lights were not feasible for this type of three-legged intersection. In response, the township applied for and was given permission to spend federal demonstration dollars on a roundabout.

Supervisor Georgia Brutscher said money received from the county when the juvenile detention facility was approved is being used to pay for the plan’s engineering and design work.

Conary noted that the original design was initially rejected by PennDOT and after a long delay of reorganization; the state came back with suggestions.

According to Linahan, since the cost of the project will exceed the amount of federal funds supporting it, the state will find ways to offset any additional costs as long as the township adheres to several state controls, first and foremost being the preservation of the existing bridge along route 52, just south of the proposed site.

Linahan stated that the primary reason PennDOT has not approved the plan is concern over the headlight sight distance required while traveling along 52 North prior to entering the round-a-bout, “they say you can’t see far enough ahead for a 45 mph speed.” He stressed that the roundabout “is only going to be 20 mph” and felt confident that once further information was passed along to the state, the design would be acceptable and the final design process would begin.

Township residents questioned what additional measures would be taken to alleviate the blind spot that exists when entering the area from the south. Linahan said, “Lots of extra things can be done…rumble strips, flashing lights above advance signs, lighting the roundabout or reflector strips which collectively will bring awareness to people that something’s coming up.”

If plans go as scheduled, construction would begin in the spring of 2013 and take approximately six months to complete. Road closures would take place in three stages; with the final stage closing the entire area to finish the project. Linahan said the final stage would most likely occur during the summer, to coincide with the school district’s summer break.

In the meantime, Conary advised residents that a left turning lane from southbound 52 onto Pocopson Road should be completed by the end of next summer.  Conary said this would help to alleviate the back-up at this intersection when commuters and buses are travelling to Pocopson Elementary School – especially once traffic is converted away from route 926 during replacement of the Brandywine Creek bridge.  That replacement is tentatively scheduled to begin in 2014 and will take at least two years to complete.

If plans for the round-a-bout are not approved by the end of 2012, the project would have to be pushed off until after the 926 bridge replacement, perhaps in 2017 or beyond.

   Send article as PDF   

Share this post:

Related Posts

4 Comments

  1. Steve J says:

    October 2 is here and the progress on the roundabout IS no futher that it was in June. Just took a look at the site and its a mess with no progress from when I looked at it in June.

    the completion date was end of September 2014. Leave it to Penn DOT and Pocopson twp to mess up a completely good road.

    IS anyone complaining to Penn DOT and Pocopson twp that the contractor completely miss there completion date…………

    it will be years till its completed!!!

    • Mike McGann says:

      None of the delay really appears to be the fault of the contractor, Road-Con. They were ahead of schedule when work largely stopped on June 19 for the utilities to be moved. It has taken all this time since — PECO moved Aug. 6, Verizon appears to have done it last week with two more utilities to go — for the utilities to schedule the moves. And while its frustrating — I live here, too — it won’t be years, but it does appear to be more like year’s end before we can expect the roundabout to open.

  2. Steve B says:

    Another huge waste of money and major inconvenience with no benefit to anyone. The problems with this intersection could be easily solved with stoplights that would be a fraction of the cost, not require extended closure of the road, and ulimately be safer. They are taking these roundabouts out in NJ because they are too dangerous and putting up stoplights at intersections.

Reply to Steve B Cancel Reply